Ohio Drive Construction
|
| Location:
|
Frisco, Texas
|
Client
Contact: |
Mr. Michael Bulla
6101 Frisco Square Blvd
Frisco, Texas 75034
(972)-292-5400
|
| Client:
|
City of Frisco
|
| Design:
|
Feb 2004 to Sep 2005
|
| Construction: |
Feb 2003 to Oct 2003 |
Contractor:
|
Lacy Construction
|
| Design Team:
|
Chad A. Pendley
John Elliott
J. Don Wortham
Wesley Lawson
|
Construction Cost: |
$1,527,532 |
|
Project Description: |
|
This project involved the design of approximately 3700 L.F. of 4-Lane divided thoroughfare through mostly undeveloped area, and included storm sewer, water, irrigation, and illumination, between Lebanon Road and Wade Boulevard in Frisco, Texas. The storm sewer design included over 2700 linear feet of RCP ranging from 18” to 42” in size. Offsite storm drainage improvements along Wade Boulevard were required to accommodate the proposed drainage from Ohio Drive. The project also required preparation of right-of-way acquisition documents. |