Independence Parkway Construction North (Eldorado Pkwy to City Limits)
|
| Location:
|
Frisco, Texas
|
Client
Contact: |
Mrs. Cissy Sylo, P.E.
6101 Frisco Square Blvd
Frisco, Texas 75034
(972)-292-5400
Mr. Richard Wilkinson
6942 Maple Street
Frisco, Texas 75034
(469)-633-6000
|
| Client:
|
City of Frisco/ Frisco I.S.D.
|
| Design:
|
Mar 2004 to May 2004
|
| Construction: |
June 2004 to May 2005 |
Contractor:
|
Charter Builders - (JRJ Paving / KCK Construction)
|
| Design Team:
|
Chad A. Pendley, John Elliott, Frank Canedy
|
Construction Cost: |
$1,603,000 |
|
Project Description: |
|
The Independence Parkway Construction North project is a joint effort between the City of Frisco and Frisco ISD to provide thoroughfare access to the Sam Roach Middle. The project included approximately 2,800 linear feet of 2-lane and 4-lane (ultimate 6-lane) divided roadway, storm sewer, water, sanitary sewer, and illumination design. The design of the storm sewer system includes over 2800 linear feet of main trunk line ranging in size from 21” RCP to 42” RCP. The water line design called for over 1,900 linear feet of 36” Ductile Iron pipe and over 2,900 linear feet of 12” PVC pipe. The sanitary sewer system included over 4,600 linear feet of new pipe ranging from 8” to 12” diameter and presented challenges to avoid conflict with an existing 20” high pressure gas transmission line at two separate locations. Legal descriptions, exhibits, and maps were also provided for right-of-way and easement acquisition. |